Short Answer

set_output_delay describes what happens outside your block's boundary — specifically, the receiving device's early and late timing requirements relative to its own reference clock. Min and max values aren't interchangeable defaults — they represent the receiver's best-case and worst-case requirement, and both need to be explicitly verified, not just one "typical" number.

Technical Reference DiagramHow do you audit output-delay constraints?

Technical Explanation

  • Check that the reference clock is actually the correct one the receiver uses, that the edge (rising/falling) and sign convention match the interface spec, and that the values themselves match what the external device datasheet or interface agreement actually states.
  • A constraint that's syntactically valid but numerically wrong — say, using the wrong reference clock or an inverted sign convention — will pass every internal sanity check while still describing a physically incorrect interface requirement.

What To Check

  • Warning sign: Outputs have only setup-like max requirements or use the wrong virtual clock.
  • Inspect: Compare one named object across the related reports; the same object should tell a consistent story.
  • Correct: Correct the boundary budget at the source and inspect representative output timing paths.

Command Checks & Actions

  • report_ports -output_delay [get_ports *]: shows boundary constraints and electrical assumptions
  • check_timing: finds missing or inconsistent timing setup

Run the commands in order. Each line answers a separate part of the check.

Healthy, Suspicious & Hard-stop Results

  • Expected: Verify receiving reference clock, edges, sign convention, min/max values, and whether the external requirement matches the interface specification.
  • Stop before floorplanning when required logic or timing coverage is missing or unexplained.

Common Mistake

The Trap: Do not assume the check passed just because ICC2 continued. Fix or narrowly justify the named objects, then rerun the same command.

What The Interviewer Is Testing

Be ready to explain why this matters before floorplanning.

Follow-up Question & Model Response

Model response: “I would save the report, inspect one affected object in the correct block and scenario, and make or request this correction. ”

Physical Design & Planning Handbook

Dive into 14 comprehensive chapters covering netlist sanity, FinFET grids, macro placement, power grids, CTS, and timing budgeting.

Offline PDF Bundle

Want all 1109 questions offline?

Get the complete 4-book PDF bundle (PnR, STA, MMMC, Low Power) with a clickable table of contents - no ads, no internet needed.

See what's inside the bundle
Timing Constraints (SDC) Handbook — nine chaptersSDC ConstraintsNine chapters on clocks, exceptions, and constraint linting.